Chapter A01
Efficiency vs effectiveness
Efficiency compares actual output with the standard output for the same input; effectiveness compares output with the goal.
Chapter A02
PERT: chance of meeting a deadline
List the critical-path activities as optimistic, most likely, pessimistic times. te = (o + 4m + p) ÷ 6 and σ = (p − o) ÷ 6; path variance is the sum of activity variances.
Chapter A03
Span of control (Graicunas) and layers
Graicunas: possible relationships = n(2ⁿ⁻¹ + n − 1). Layers needed: keep grouping staff under one manager per span until one manager remains.
Chapter A05
Motivation: Vroom expectancy
Motivational force = Expectancy × Instrumentality × Valence. E and I from 0 to 1; V from −1 (unwanted) to +1 (highly wanted).
Chapter A05
Communication channels in a team
Possible two-way channels = n(n − 1) ÷ 2. Useful when deciding team size and reporting lines.
Chapter A06
Control: budget variance and management by exception
Cost lines are adverse when actual exceeds budget; revenue lines (r) are adverse when actual falls short. Lines beyond the tolerance are flagged as exceptions.
Educational calculators with simplified, stated assumptions. They do not replace bank policy, regulatory returns or professional advice.